🎴Project 1

Kilgore Tract Project 1:

2,615 feet of 8-foot trails along Kansas and connects to Heritage Park

Estimated Construction Budget: $600,000.00

  • Anticipated Bid Phase: Spring 2027
  • Anticipated Construction Phase: Fall 2027.

Photo updates will be available once construction begins.

🌳Project 2

Kilgore Tract Project 2:

  • 1,400 feet of 8-foot trails
  • 2 overlooks

Estimated Construction Budget: $1.85 million

  • Anticipated Bid Phase: 2028
  • Anticipated Construction Phase: 2028.

đź‘€Photo Updates of Project Progress

Photos available once construction begins. Follow this page to receive email updates on both Phase 1 & 2.