Asphalt Street Rehabilitation Project Drop-Down Menu: Descriptions and FAQs.

Please select the project of interest by clicking the drop-down to learn more about each street rehabilitation for 2026.

Project Status Update 3/3/2026

Visible deficiencies were noticed during construction which triggered additional construction materials testing. City Staff and design engineers are reviewing the construction materials testing results to determine the best approach to make corrective actions.

An old, galvanized water line located under the roadway was noticed to be leaking causing some subgrade stability concerns is scheduled to be replaced and relocated by April 2026.


Clear Creek Avenue Rehabilitation Description and Funding.

This project is designed to improve Clear Creek Avenue while maintaining infrastructure integrity using League City Reinvestment Program and Community Development Block Grant (CDBG) funding. The total budget is $425,223.

During construction, Clear Creek Avenue lanes will be one way traffic to maintain resident access.

  1. How long will construction last? Construction is scheduled to begin the first part of January 2026 with total completion by end of February 2026.

UPDATE: Corrective actions to the substantial deficiencies with this replacement are underway. This project will now last through May of 2026.

  1. What happens to my mail and trash services during the reconstruction of Clear Creek Avenue? Mail and trash are anticipated to maintain normal service.
  2. Will I have access to my driveway? Yes, the contractor will maintain driveway access.
  3. What is the benefit of this project? This project will improve rideability and maintain the integrity of Clear Creek Avenue.

Asphalt Rehabilitation "Package 8"

This project will fix and improve several streets as part of the City’s yearly road repair program. The work includes repairing the road base, adding new asphalt, and rebuilding parts of the road on:

  • Bern Street
  • Boden Street
  • Austin Street
  • Landrum Street
  • 7th Street.

Capital Improvement Project Budget: $2M

Project Timeline:

  • Current Status: Bid Phase: March 2026
  • Design Phase: Completed September 2025
  • Anticipated Construction Phase: June 2026
  • Anticipated Substantial Completion: Anticipated Summer 2027

Update photo available once construction begins on each rehabilitation street.

Asphalt Rehabilitation Hot Spot Map FY2026

This map shows each active and upcoming asphalt rehabilitation project in League City. Please click on the flashing icon to learn more.

Clear Creek Avenue Asphalt Rehab
League City Listens logo

Contact Us

Have questions or want to learn more about a project, contact us below:

Contact Information
Name City of League City
Phone 281-554-1265
Email Amber.Pedigo@leaguecitytx.gov