Asphalt Street Rehabilitation Project Descriptions and FAQs.
Clear Creek Avenue Rehabilitation Description and Funding.
This project is designed to improve Clear Creek Avenue while maintaining infrastructure integrity using League City Reinvestment Program and Community Development Block Grant (CDBG) funding. The total budget is $425,223.
During construction, Clear Creek Avenue lanes will be one way traffic to maintain resident access.
- How long will construction last? Construction is scheduled to begin on December 1, 2025, with final completion by the end of January 2026.
- What happens to my mail and trash services during the reconstruction of Clear Creek Avenue? Mail and trash are anticipated to maintain normal service.
- Will I have access to my driveway? Yes, the contractor will maintain driveway access.
- What is the benefit of this project? This project will improve rideability and maintain the integrity of Clear Creek Avenue.
This project has not yet gone out for bid. Please follow this page and check back for updates. Package 8 is set to tentatively include asphalt rehabilitations for Bern Street, Boden Street, Austin Street and Landon Street with possible alternates.

Asphalt Rehabilitation Hot Spot Map FY2026
This map shows each active asphalt rehabilitation project in League City. Please click on the flashing icon to learn more.