Lobit Park
🚧Phase 1
Lobit Park Construction Timeline
-
Timeline item 1 - complete
Phase 1: Design & Master Plan stage
Design ran concurrently with the Master Plan development. A public hearing was held Monday, September 16th at 6 p.m. at the Johnnie Arolfo Civic Center located at 400 West Walker Steet.
-
Timeline item 2 - complete
Phase 1: Workshop and Bid Approval
City Council Workshop approved Phase 1 on September 24, 2024. Bids for the project opened in August of 2025 and the contract was awarded by City Council on September 23, 2025.
-
Timeline item 3 - active
Phase 1: Construction Stage
The park is expected to reopen later this fall and will remain open as Phase Two gets underway.
- A pre-construction meeting was held October 2025
- Lobit Park closed to the public October 13, 2025
- Construction began on October 20th.
NOTE* Due to bad weather conditions, Phase 1 construction is expected to be completed in September 2026.
🏗️Phase 2
Phase 2 design and construction include:
The next phase will bring even more improvements, including a
- Reconstructed parking lot
- Two new soccer fields
- Shade structure over the basketball courts
- Renovated restrooms
- New pedestrian bridge connecting the park to the island.
- Large detention pond for improved site drainage
The bridge will feature a pergola, creating a welcoming spot to enjoy the park’s surroundings
Phase 2 Timeline
-
Timeline item 1 - complete
Design Phase
Current Status: Design phase anticipated to be completed in April 2026.
-
Timeline item 2 - complete
Bid Phase
Anticipated bid date in Spring 2027
-
Timeline item 3 - incomplete
Construction Phase
Anticipated construction phase Summer 2027
-
Timeline item 4 - incomplete
Substantial Completion
Anticipated substantial completion Summer 2028